Timeline

January 2021
Project kick-off
January 2021
June 2021
Choice of concept tank design
June 2021
February 2022
Design documentation to be sent to shipyards for competitive tender
February 2022
February 2022
Ship financing and insurance model finalized
February 2022
June 2022
Conceptual designs for LH2 systems finished
June 2022
June 2022
Configuration of power system
June 2022
June 2022
Ship building contract signed
June 2022
November 2022
Performance test of fully integrated energy management system
November 2022
June 2023
Launching vessel
June 2023
October 2023
Delivery of vessel
October 2023
October 2023
Systems installed and tested aboard ship
October 2023
December 2023
Vessel approved. Operation starts!
December 2023
March 2024
Reporting on 12-month operation
March 2024